Burlingame Broadway Grade Separation: Costs, Timeline and Station Plans

"I know people have hopes it will stay open, but I'm telling you, the practicality of that is zero." Councilmember Donna Colson said that about the Broadway Caltrain station at the April 7 City Council meeting where Burlingame ended the Broadway Specific Plan, according to the San Mateo Daily Journal.

As of October 2026, nobody is working at the crossing, there are no detours, and the earliest possible groundbreaking is two years away. Even so, the biggest decision about Broadway's future has already been made. Burlingame gave up the station so it could afford to lift the tracks. That trade is why the project is moving again. It also took apart the plan that was supposed to guide Broadway's next 20 years, and it sets where people on the north end of town will walk, bike and catch a train once the work is done.

The trade, in dollars

The California Public Utilities Commission ranks Broadway as the highest-priority grade separation project in the state. The same tracks carry Union Pacific freight, which is the only freight rail link between San Jose and San Francisco. For years the plan was to raise the tracks and rebuild the station along with them. Then the cost estimates arrived.

Estimate What it covered Source
About $316 million Original estimate for the station-included project Daily Journal
$889 million to $899 million Station-included design after cost increases; Daily Journal stories give both figures Daily Journal
$615 million Station-free design, assuming a 2026 construction start, as of March 2025 Caltrain
$653 million Same station-free design, assuming a 2028 start, as of March 2025 Caltrain
$662.48 million Station-free design at 65%, assuming a November 2028 start and four years of construction, as of September 2026 Caltrain staff report

Caltrain's project page describes what happened next. In early 2024, new estimates showed construction costs had risen sharply, so Caltrain, the City of Burlingame and the San Mateo County Transportation Authority reopened the scope together. In March 2025, the City Council agreed to move forward with a design that has no Broadway station. Dropping the station also meant dropping the temporary "shoofly" tracks that would have carried trains around the work zone during construction.

The newest figure is higher than the $615 million number from 2025, and the design did not grow to cause that. SMCTA's September 2026 board packet puts the increase mainly on three assumptions: construction now starts in 2028 instead of 2026, it lasts four years instead of three, and annual cost escalation went from 3.5% to 5%. In other words, most of the added cost comes from waiting. Caltrain says the same on its project page: "Our goal is to begin construction as soon as possible to avoid further cost increases brought on by delays."

What the station decision did to the Broadway Specific Plan

The Broadway Specific Plan proposed transit-oriented, mixed-use development for the district, including more housing and less parking. The plan depended on the station. The Daily Journal reported that without a station, the Broadway district no longer automatically qualifies as transit-oriented development with dense, parking-free zoning, and the plan had relied on that status for both its funding and its design.

Councilmember Michael Brownrigg told the paper that the council was "backing down because of the uncertainty with grade separation and what that community is going to look like." Community Development Director Neda Zayer said the area's existing land use standards already allow more housing and larger buildings than are being built today. She added that the city can encourage private development with tools other than a specific plan.

The merchants wanted the plan to continue. John Kevranian, who owns Nuts for Candy and was president of the Broadway Business Improvement District at the time, wrote to the council in an email the Daily Journal quoted: "We, the Broadway merchants, request the City of Burlingame to have a VISION for Broadway Business District." Brownrigg pointed to a reason for optimism that does not need a station. Once the crossing is grade-separated, it could calm traffic in the area and make Broadway more attractive to customers.

Why weekday trains are not coming back first

Today the Broadway stop has weekend service only, and Caltrain's current timetable lists Broadway on the weekend schedule. Broadway business leaders have asked for weekday service to return while the city works on funding. In a resignation letter dated October 2 that the Daily Journal quoted, Kevranian wrote that when weekday service ended more than 20 years ago, "the negative impact was immediate and profound."

The same article gave Caltrain's two objections. Weekday stops would add to congestion at an intersection that already has problems, and the current station layout makes passengers cross live tracks. Under the approved scope the station goes away permanently. None of the material reviewed for this post gives a date for when weekend service at Broadway would end.

What gets built in place of a platform

These are the changes that will matter day to day once construction ends:

  • Raised tracks on a narrower elevated guideway. Trains run above Broadway, and road traffic no longer crosses the rails.
  • Two new pedestrian and bike undercrossings. They go in near Cadillac Way and Sanchez Avenue and connect to a set of walking and biking improvements.
  • The Morrell crossing goes away. The at-grade, pedestrian-only crossing at Morrell is replaced by the two undercrossings north of it.
  • Walking and biking along Broadway stays. The project keeps bicycle and pedestrian access along the street.

Without a station, the project's public-space investment goes into these east-west connections instead. Caltrain's July 2026 update to the City Council says the redesign refined the guideway, structures, landscape design and aesthetic options. The update does not include renderings or findings on how the structure will look from nearby blocks, so that detail is still to come.

The calendar from here

  1. June 2026: Staff finished the 65% design and an updated cost estimate.
  2. August 2026: The City, SMCTA and Caltrain agreed to take the project to 100% design. On August 17, Burlingame committed $2.4 million toward final design.
  3. September 3, 2026: The Caltrain board took up a $24 million budget increase for final design. Burlingame covers up to 10% of that and SMCTA up to 90%.
  4. At 95% design: The cost estimate is updated again and used in the guaranteed maximum price negotiation with the contractor.
  5. November 2028 at the earliest: Construction could begin, subject to funding. Caltrain says the partners are still working to close funding gaps for later phases.

The current estimate assumes about four years of construction. No official completion date has been published. A late-2032 finish only works if everything starts on time.

Details about street disruption are still open. SMCTA's status report says the team is still evaluating options for staging closures on Broadway and is still analyzing operations and detours for the Carolan and Cadillac crossings. Property work is still in early steps such as assessments, appraisals and plat maps. The September estimate sets aside $25.78 million for real property and easements but does not list specific parcels. That report covers January through March 2026 and sets no date for those decisions.

Broadway, meanwhile, keeps opening doors

Patty's Retro Diner opened at 1184 Broadway in February 2026 and held its grand opening on March 12, Palo Alto Online reported. In May, Burlingame Voice reported that a new tenant had secured the lease on the former Sam's Sandwich space in the old Greyhound Depot. Readers commenting on the post identified the tenant as Gigi's Café, and a June 1 comment said the owner hoped to move by fall 2026 or early 2027.

Both businesses are opening on a street where, according to Zayer, current zoning already allows more than has been built, and where final design of the crossing is now funded through the $24 million budget increase.

If you own a home near Broadway and want to know how a multi-year rail project timeline figures into its value today, LeDoux Group can walk you through it with the current project documents on the table. Request Your Free Home Valuation, and we'll include what final design means for your block.

Work With Us

Real estate is not just about homes, but people. Relationships create the personal and rewarding experience that home buyers and sellers deserve.
Contact Us